Commissioning (Cx) Services
New Building/Systems Commissioning
- Pre-Design Phase
- Assist in development or review Owner Project Requirements (OPR)
- Cx scope development
- Cx Plan development
- Design Phase
- Assist in development or review of Basis of Design (BOP) document
- Prepare Cx specifications
- Construction document review
- Prepare Pre-Functional Checklists
- Develop Functional Performance Test (FPT) Procedures
- Maintain Cx Issues Log
- Construction Phase
- Review shop drawing submittals
- Update FPTs
- Conduct periodic site observations
- Observe selected startup and prefunctional checklist procedures
- Review BMS/DDC trends and reports
- Update ongoing Cx Issues Log
- Acceptance Phase
- Perform verification checks
- Direct/document FPTs
- Issue FPT report
- Review Operations and Maintenance documents
- Personnel training management
- Complete equipment warranty reviews
- Update ongoing Cx Issues Log
- Post-Acceptance Phase
- As-built document review
- Direct/document seasonal FPTs
- Prepare final Cx report
- Prepare trend log package
- Warranty issue resolution
Existing Building/Systems Retro-Commissioning
- Application
- Prepare application for outside funding when available
- Planning
- Initial site assessment
- Develop Retro-Commissioning Plan
- Identify potential operation improvement
- Identify potential energy savings measures
- Develop implementation costs and energy savings projections
- Implementation
- Work with team to implement recommendations
- Finalize detailed site assessment
- Develop targeted FPT procedures
- Collect and analyze trend data
- Verification
- Verify installation and proper operation of retro-commissioning measures
- Update energy savings based on measured data
- Prepare final report